(Above) Rendering of Marina Plaza, a room on the Chicago Riverwalk between State and Dearborn Streets. (Click on images to view larger versions.)
Delays dont faze Riverwalk planners
|
October 1, 2014 Despite delays, a stretch of Riverwalk between State Street and Clark Street will be substantially complete by mid-December, the Chicago Department of Transportation said on Monday.
All the cement work and all the hardscape will be complete by then, said Peter Scales, CDOTs director of public affairs. The landscaping, you cant really put that in the middle of winter, so thats going to have to go in early spring.
By March 2015, three blocks of the Riverwalk, from State Street west to LaSalle Street, will be open to the public. Each block will have its own style designers refer to each block as a room and its own name. Marina Plaza runs from State Street to Dearborn Street in front of Marina City, The Cove stretches from Dearborn to Clark, and River Theater sits between Clark and LaSalle.
It took a Freedom of Information Act request to get this update. Scales spoke with Loop North News after ignoring requests for information and comment for several months.
He acknowledged construction delays, believed to have put the project as many as eight weeks behind schedule, but said the entire project will be done on time.
We had some schedule setbacks due to the severe winter weather and the floods from the summer rain that occur every once in a while, which has put us back several weeks, said Scales. By and large the entire Riverwalk improvement project remains on schedule to be complete by 2016.
Scales clarified a claim in September by Riverwalk architect Carol Ross Barney that the city has not borrowed the full $98.6 million for which it has been approved by the United States Department of Transportation.
The money comes from the Transportation Infrastructure Finance Innovation Act, a program that provides federal assistance for infrastructure projects across the nation. The Chicago Riverwalk is the programs first project.
Its our intention to utilize the entire amount of the TIFIA loan and to borrow up to the amount of $98.6 million, says Scales.
The city gets the money back, he explains, only after it spends it.
The reimbursements come in [after] you make the expenditures so weve only gotten about seven million dollars in so far to cover those costs. But thats just the way that funding mechanism works. You make the expenses and then you essentially apply for the money.
He says to date TIFIA reimbursements have totaled exactly $6,908,963.81.
| Barney (right) was concerned that less money was available for design of the Riverwalk farther west. She told Loop North News that construction of the Riverwalk near the confluence, where the main branch of the Chicago River splits into the north and south branches, will not be as elaborate as originally planned. | ![]() |
- Previous story: Unmarked telephone equipment caused Riverwalk delay in July
- Related story: Riverwalk construction eight weeks behind schedule
- More photos: Riverwalk construction
